Subdivision Developer - Requirements

The following is required to process your application for electric infrastructure for a residential development:

  • Completed application-each work order project requires a separate application and design fee.
  • Required documents outlined on application
  • Design Fee

 

Applications

Application for Subdivisions & PUD Development Infrastructure (pdf)

Application for Feeder Line Relocation/Conversion to Underground (pdf)

Mail your completed application, required documents, and design fee to:

United Power, Inc.
Consumer Relations & Electric Design Dept.
PO Box 929
Brighton, CO 80601
-or-
500 Cooperative Way
Brighton, CO 80603

Incomplete application packets will not be processed.

 

After Receipt of Completed Application Packet:

  • A representative of United Power will contact you to meet on site if necessary.
  • Approximately 21 days after your submittal, you will receive a preliminary design.
  • Approximately 30 days after you have submitted your signed preliminary design, you will receive a final design, agreement, and invoice.
  • Once United Power receives your signed final design, signed agreement, and total payment, and if all right-of-way issues are clear, your project will be placed on the construction schedule. Please note that construction of your project will start approximately three weeks after it is placed on the construction schedule.
  • The Construction Coordinator will contact you for a pre-construction meeting prior to construction.

 

Locating of Existing Underground Utilities

In compliance with Colorado State SB93-155, all existing underground utilities and other facilities must be marked prior to excavation. United Power will call the Utility Notification Center of Colorado 48 hours prior to the start of any excavation and request marking of all public utilities.

It is the customer's responsibility to verify, mark and provide a sketch of all customer-owned underground utilities and other facilities within the area of planned excavation. (Subdivision, Commercial/Industrial, and Multi-Unit Commercial builders: these utilities include developer installed water, sanitary sewer, storm sewer and irrigation facilities installed in conjunction with a subdivision or other land development project not yet accepted by the affected jurisdiction.)

United Power construction will not begin until all underground lines and private facilities are marked and United Power has received a sketch and signed copy of the Private Facilities form (pdf).

 